Equipment layout basic admin — August 14, 2021 · Comments off Equipment layout must show the following: All equipments including tanks, vessels, process Pumps and other rotating machinery giving three locating Co-ordinates. 1) Package items 2) Pipe racks 3) Electrical & instrument cable trays. 4) MCC and control rooms 5) A/C ducting 6) Offices & maintenance areas 7) Building features including columns, beams, walls, floor Openings, staircases, passages etc. 8) Show tube removal space for heat exchangers 9) Show monorails lifting bays & hoists etc. Consideration must be given to the following while ● Developing equipment layouts ● Process requirements ● Operations & maintenance requirements ● Hazardous area classification ● Safety requirements ● Factory inspector’s requirements ● TAC requirements ● Civil requirements ● Erection / dismantling requirements ● Future provisions