Sr.No. | Item Description | Percentage of Capital Cost | |
Liquid Lines | Gas Lines | ||
1 | Survey, ROW and Compensation | 2% | 1% |
2 | Line Pipe Steel Cost | 33% | 45% |
3 | Main Line Materials | 2% | 3% |
4 | Coating of Pipes | 11% | 6% |
5 | Main Line Construction | 33% | 25% |
6 | Cathodic Protection | 1% | 1% |
7 | Telecommunications, SCADA and RCPs | 5% | 2% |
8 | Pump / Compressor Stations | 5% | 12% |
9 | Delivery Terminal Facilities | 2% | 1% |
10 | Project Management | 5% | 4% |
SubTotal | 100% | 100% |