Cost Breakup for a Pipeline Project

Sr.No.Item DescriptionPercentage of Capital Cost
Liquid LinesGas Lines
1Survey, ROW and Compensation2%1%
2Line Pipe Steel Cost33%45%
3Main Line Materials2%3%
4Coating of Pipes11%6%
5Main Line Construction33%25%
6Cathodic Protection1%1%
7Telecommunications, SCADA and RCPs5%2%
8Pump / Compressor Stations5%12%
9Delivery Terminal Facilities2%1%
10Project Management5%4%
 SubTotal100%100%

 