Clause | Details |
PME-RES-001 | Piping Material Engineer is required from Bid Stage, through design, construction and mechanical completion stages. |
PME-RES-002 | Peak period of work is early in the project when PMS to be developed and bulk inquiry requisitions are sent to vendors. |
PME-RES-003 | Develop Piping Material Specifications for Process and Utility Services. |
PME-RES-004 | Develop Fabrication/Welding Specification. |
PME-RES-005 | Develop Shop and Field Testing Specification. |
PME-RES-006 | Develop Insulation Specification |
PME-RES-007 | Develop Painting Specification. |
PME-RES-008 | Develop Datasheets for Process and Utility Valves |
PME-RES-009 | Develop Special Items List for Steam Traps, Strainers, Hoses etc. |
PME-RES-010 | Develop Data Sheets for Special Items. |
PME-RES-011 | Assemble piping material requisition with additional Documents. |
PME-RES-012 | Develop Technical Supply Conditions / Requirements for Various Piping Materials. |
PME-RES-013 | Review offers from vendors and create a technical bid evaluation. |
PME-RES-014 | Make a technical recommendation. |
PME-RES-015 | After placement of a purchase order, review and approve documentation from vendors related to piping components. |
PME-RES-016 | When required, visit the vendor’s premises to attend kickoff meetings, the testing of piping components, or clarification meetings. |
PME-RES-017 | Liaise with the following departments: Piping Design and Stress, Process, Instrumentation, Vessels, Mechanical, Structural, Procurement, Material Control. |
PME-RES-018 | Make sure that everyone in the piping group is aware of the materials of construction that can be used for piping systems. |
PME-RES-019 | Prepare MTO. |
PME-RES-020 | Help 3D Administrator in creating PMS in 3D Softwares like PDS, PDMS etc. |